What is the CNC plate drilling machine assembly and commissioning process? Tomorrow equipment will be dismantled for painting. Today is am in factory to give you report.
1.Install the bridge joint (which can connect two worktables), worktable, and adjust the level.
2.Install the linear guide rail and ball screw.
3.Install T-slot (used for clamping tools and workpiece)
4.Install gantry part. Firstly linear guide rail, ball screw, then drilling heads.
5.Hydraulic station, connect to electricity for commissioning.