Dear friends, let share the tips of our CNC plate drilling installation.
1.Foundation leveling
Use level gauge to observe the height of the pre-buried plate, make the highest buried plate as the datum.
Dear friends, let share the tips of our CNC plate drilling installation.
2.Machine bed installation
Put the bed of two sides on the foundation plate while measure the width of bridge, the width of the distance of the beds should be 5mm wider the than the bridge for bridge installation.
3.Machine bed leveling
Level the highest side of the foundation plate.
4.Machine bed leveling of another side
Put the bridge on the leveled side of machine bed, put the level gauge on the bridge to level another side of the machine bed.